Chat Transcript of Simplilearn Virtual class I on MS Project
Below is the transcript of the virtual class-I on Project Scheduling using MS Project on 12th November, 2009 .
Krishna was the instructor of the session
Jamal has joined the meeting.
Attendee16 has joined the meeting.
Jamal has left the meeting.
Kanchan has joined the meeting.
jamalos has joined the meeting.
arun nampoothiri: Can different calenders be used in one project?
Sampath has joined the meeting.
Attendee18 has joined the meeting.
Kanchan has left the meeting.
Attendee18 has left the meeting.
Srinivasan: Yes. We can use different calendars for different resources
arun nampoothiri: e.g engg., procurement and construction
Srinivasan: working from different locatoins
arun nampoothiri: ok
arun nampoothiri: WBS
Senthil has joined the meeting.
jamalos has left the meeting.
Attendee18 has joined the meeting.
Chakrapani has joined the meeting.
Attendee18 has left the meeting.
Chakrapani: sorry for being late… was stuck in a meeting
Chakrapani: i hope i have not missed a lot
arun nampoothiri: can different type of resources be assigned to one activity – eg. manpower, machineries & materials ?
Chakrapani: great
Attendee10: yes
arun nampoothiri: ok
arun nampoothiri: yes
arun nampoothiri: I understand. I am from engineering & construction background in petrochemicals & refineries
Attendee41 has joined the meeting.
arun nampoothiri: After scheduling, can we extract a report which can show a summary of the project – eg. total no. of activities, critical activities, open ended activities etc.
arun nampoothiri: ok
Attendee16: if an approved baseline has to be changed then? do we re baeline it track with latest one
Attendee16: ok. i understand FIRST baseline and that can keep changing. am i right?
Attendee16: ok
Attendee16: ok
Nitin Hajela has left the meeting.
Attendee10: i agree with you
Attendee16: thank you
Attendee16: click full screen…
Attendee16: sure
Attendee10: u can share your desktop
Sougat Mitra: No
Attendee10: yes
Attendee42 has joined the meeting.
Chakrapani: yes
Sathya: no, server unreachable error be shown
Attendee16: yes
anu has left the meeting.
Abid: i can also see
arun nampoothiri: yes, visible
Sathya: now I can
anu has joined the meeting.
Yoav Reshef has left the meeting.
Attendee42: i can see the screen – but its intermittant, can you please move slow,its taking time to refresh
Jagdish has left the meeting.
Yoav Reshef has joined the meeting.
Senthil has joined the meeting.
Sathya: audio is gone
Chakrapani: sathya relogin
Chakrapani: no
Senthil: Yes
Srinivasan: we are able to hear you.
Chakrapani: i can hear
Senthil has left the meeting.
Attendee10: ur screens are taking time to reload
Attendee10: cant see ur msproject
Jagadish has joined the meeting.
arun nampoothiri has left the meeting.
Sampath: proj name also mentioned as task ?
Attendee10: we can also right click on left pane and select indent
Srinivasan: Krish, you may want to keep the task bar visible
Attendee42 has left the meeting.
Sampath: ok thx
Attendee10: ok
Srinivasan: Yes
Sampath: yes
Attendee10: yups
Jagadish: yeah thanks
Chakrapani: Krishna… under the project menu do need to define the project start date
Chakrapani: ok
Jagadish: can u please repeat details about fixed date
Jagadish: fixed duration
Jagadish: oh ok – i got it, thanks
Attendee10: we can also manage the total efforts for the project.
Arun Nampoothiri has joined the meeting.
Srinivasan: We need the duration column as it would tell us the duration when we use more than one resource for the same activity .
Tarek Moujahid has left the meeting.
Srinivasan: Okay
Srinivasan: Thanks
anu has left the meeting.
Srinivasan: Yes
Jagadish: yeah
Sampath: yes
Abid: yes
Attendee10: yups
Arun Nampoothiri: yes
Chakrapani: yes
Attendee16: can you show the spreadsheet again?
Attendee16: pls explain activity 9s columns
Attendee16: thank u
Attendee16: what is 2ss nd 3ss?
Attendee16: okok
Attendee16: one sec
Sougat Mitra: No sound
Attendee16: how come 9 depends on 8?
Attendee10: got that
Attendee16: ok
Srinivasan: Yes
Chakrapani: what is the time each resource is spending on the activity
Attendee16: go ahead
Jagadish: yeah please proceed
Sampath: yes
Sathya: yes
Attendee10: yes
Sougat Mitra has left the meeting.
Chakrapani: not that… some of the resources are required only say for and hr a day
Chakrapani: in that case thre is always change to the schedule
Chakrapani: ok
Attendee10: ceate an activity and assign 1 hr per day
Attendee10: and we want to track efforts spent in those meetings
Attendee10: k
Ajay Khullar: good job
Ajay Khullar: yups
Attendee16: clear now
Ajay Khullar: clear now
Arun Nampoothiri: any provision for cost
Ajay Khullar: can you please explain it again?
Srinivasan: In the resource sheet, you can provide the cost.
Srinivasan: There is a standard rate and overtime rate.
Chakrapani: now on the screen you have baseline start and start
Chakrapani: what does this start indicate
Chakrapani: ok
Chakrapani: is this start the actual start
Srinivasan: You were planning to explain the Lag time
Chakrapani: so basically there are 3 start dates
Srinivasan: Yes.
Chakrapani: baseline, start and actual
Ajay Khullar: yes
Jagadish: hey krish, this is really a wonderful session.Please excuse me I go to leave for a meeting
Chakrapani: now my dates are not matching with yours
Chakrapani: i am on ms proj
Jagadish: thanks krish
Arun Nampoothiri: is there any limit for no. of activities?
Chakrapani: sure
Sampath: thx krish . u guys doing a good job
Srinivasan: Thanks Krish.
Arun Nampoothiri: ok
Chakrapani: sure thanks
Senthil: Thanks a lot
Attendee16: thank you very much
Arun Nampoothiri: thanks
Senthil has left the meeting.
Chakrapani: krish this was a wonderful session
Sathya: thanks a lot Krish, awesome session
Jagadish has left the meeting.
Srinivasan: Thanks Krish.
Attendee16: i sec
Srinivasan: Nice session..
Chakrapani: thanks a lot
Arun Nampoothiri: really useful
Abid: thank you for this session
Yoav Reshef: Thank you
Yoav Reshef: Thank you
Chakrapani: will message you on the discussion forum for any doubts
Attendee16: thank you
Arun Nampoothiri: nice one
Chakrapani: thanks once again
Chakrapani: have a nice day ahead
Attendee16: see u all in next session
Attendee16: thanks again, bye
Chakrapani: sure
Abid has left the meeting.
Sathya has left the meeting.
Chakrapani has left the meeting.
Attendee16 has left the meeting.
Arun Nampoothiri has left the meeting.
Attendee11 has left the meeting.
Srinivasan has left the meeting.
About Me
Categories
- "simpliearn reviews" (1)
- "simplilearn.com reviews" (1)
- Budget (1)
- Critical Path Method (1)
- Earned Value Problems (1)
- Earned Value Solutions (1)
- Earned Value Technique (1)
- Eligibility criteria to write PMP (3)
- Free PMP Preparation (1)
- Good Project Manager (1)
- How to pass PMP Exam (2)
- Microsoft Project (2)
- MS Project (2)
- Online Class (2)
- Online PMP (2)
- Online PMP Certification Training (2)
- Online PMP Exam Preparation (1)
- Online PMP Preparation (9)
- Online PMP Training (11)
- Online PMP Training Provider (2)
- PMI (2)
- PMP (10)
- PMP Certification Presentation (4)
- PMP Exam (1)
- PMP Exam Notes (1)
- PMP Preparation (1)
- PMP Training (3)
- PMP Training Provider (2)
- Project Management (6)
- Project Management Professional (3)
- Project Management Training (1)
- Project Risk Management (2)
- Scope (1)
- Simplilearn (9)
- simplilearn review (1)
- simplilearn user comments (1)
- simplilearn.com review (1)
- simplilearn.com reviews (1)
- time (1)
- Virtual class (3)
- What is PMI (1)
- what is PMP (1)
Friday, November 13, 2009
Online PMP training
Posted by
Simplilearn
at
2:18 AM
Labels: Microsoft Project, MS Project, Online PMP Preparation, Online PMP Training, PMP, Project Management, Project Management Professional, Project Management Training, Simplilearn
Subscribe to:
Post Comments (Atom)
0 comments:
Post a Comment